Remove and Replace Water Softener at Building 206, Fort Hunter Liggett, CA

Prime Contractor: Jacob Construction & Design, Inc.

Contract Number: W9126G-13-C-0055

Contract Value: $12,006.57

Contract Award Date: 09/27/2013

Final Completion Date: 10/27/2013

Agency: Army Reserve Contracting Center-West, Seaside, CA

Project Goal

JCD removed and replaced the existing, non-operational water softener at Fort Hunter Liggett, CA.

Description

Jacob Construction & Design was awarded the task of removing and replacing the existing, non-functional water softener at Fort Hunter Liggett, CA. Aside from a slight change to the Brine Tank’s composition, it was important to the Army that the new unit remain an exact replacement of the older outdated one. This ensured that added costs and the need for structural changes were avoided. JCD worked hard to accommodate all the Army’s requests to deliver the best value possible.

This project involved

  • Demolition of outdated Water Softener
  • Piping/Insulation
  • Installation of Water Softener/Tanks/Controller